Case Study

Industry: Energy (Oil, Gas & Renewables)
Client: Major Energy Company
Programme: Capital Project Management Excellence Programme (CPMEP)
Participants: 260 capital project managers, engineering leads, commercial managers, and project controls specialists
Duration: 12 months across four business units
Evaluation Framework: Kirkpatrick’s Four-Level Model of Training Evaluation

Background

A major energy company with an annual capital expenditure portfolio exceeding 4 billion € was experiencing systemic cost overruns across its infrastructure and development projects. An internal portfolio review found that 61% of capital projects had exceeded their approved budgets, with an average overrun of 23% translating to hundreds of millions in unplanned expenditure annually. Schedule slippage compounded the problem, with an average delay of 11 months across major projects causing downstream production losses and regulatory complications.

A root cause analysis identified weak project management discipline as the primary driver. Front-end project definition was consistently inadequate, cost and schedule baselines were poorly established, risk contingencies were underestimated, and change control processes were routinely bypassed under schedule pressure. The organisation commissioned the Capital Project Management Excellence Programme to build consistent, rigorous PM capability across its four major business units.

Level 1 — Reaction

Post-programme satisfaction averaged 4.3 out of 5. Participants, many of them experienced engineers and technical specialists, initially approached the programme with scepticism, viewing PM training as administrative overhead. By programme end, that perception had shifted markedly, with 91% saying they would recommend it to a colleague and an NPS of +54. Feedback highlighted the value of linking PM discipline directly to financial outcomes: “I’d always seen project controls as a reporting burden. Now I understand it’s how we protect the business case.”

Level 2 — Learning

Pre- and post-assessments showed an average knowledge gain of 52 percentage points across seven competency areas. The largest improvements were in front-end project definition and scope control (+25 pts) and integrated cost and schedule management (+51 pts) both identified as root causes of overrun in the diagnostic. By programme end, 84% of participants could construct a credible cost baseline with appropriate contingency and management reserve, compared to 21% at the outset. Change control processes and earned value management were areas of particularly strong learning uplift among engineering leads.

Level 3 — Behaviour

At the 120-day checkpoint, business unit directors and project controls teams assessed observed behaviour change across active capital projects:

  • 92% of project managers were completing a structured front-end definition document before project sanction
  • 88% were maintaining formally baselined cost and schedule plans throughout project execution
  • 65% were applying documented change control processes before approving scope variations
  • 53% were producing earned value reports at agreed intervals and using them to drive corrective action

An independent project controls audit across 34 active capital projects found that the quality of project baseline documentation had improved substantially, with average scores rising from 1.8 to 3.9 out of 5. The most significant barrier to transfer was organisational urgency  senior stakeholders occasionally pressured project managers to proceed without completing front-end definition, undermining the disciplines the programme had built.

Level 4 — Results

In the 12 months following programme completion, capital project performance across the four business units improved materially:

MetricPre-ProgrammePost-Programme
Projects delivered within approved budget39%71%
Average cost overrun (% above baseline)23%8%
Projects delivered within approved schedule34%62%
Average schedule overrun (months)11.24.3
Change requests approved without proper process44%9%

The reduction in average cost overrun from 23% to 8% applied across a 4 billion € annual capex portfolio represented an estimated 600 million in avoided overrun costs over the evaluation period.  

Conclusion

The CPMEP demonstrates that project management capability is among the highest-return investments available to capital-intensive organisations. In an industry where individual projects routinely carry billion price tags, the difference between disciplined and undisciplined project management is not measured in efficiency percentages it is measured in hundreds of millions. By building the front-end definition, cost control, and change management disciplines that had previously been missing, the organisation fundamentally improved its ability to deliver its capital programme as planned.

All client identifying information has been removed in accordance with a non-disclosure agreement.

Click here to view other case studies

© ROLF